OpenPlant Modeler Help

How To Move Unassigned Components to IsoSheet

  1. Open the Isosheet Manager from Pipeline Manager.
  2. Click the Pipeline List button at the top left of the dialog and select a pipeline from the list.
  3. In the Components grid, select the Component(s) not assigned to Isosheet sorting option.
  4. Select the component(s) you want to assign to a IsoSheet.
  5. Click the Move unassigned component(s) to isosheet icon.

    The Select Iso Sheet dialog displays.

  6. Select an IsoSheetfrom the list.
    Note: The list displays existing IsoSheets for the selected pipeline.
  7. Click the OK button.

    The components will be moved to the selected IsoSheet.